 |
These examples are representative of
heavy-haul rail experience. Additional experience has been acquired
through transit & commuter rail projects that have been completed by
Mass. Electric Construction Company (MEC) since 1966 and
have totaled in excess of US$1 billion. Currently, MEC is the
largest installer of transit and passenger rail based
signal-communications and traction power systems in the U.S. The
company has worked on all major transit properties and has acquired
significant knowledge of all major signal & communications equipment
and technologies. Southern
California Regional Railroad Authority (SCRRA) - METROLINK
MECRail currently provides ongoing, full-time, fully staffed,
system-wide, installation, maintenance, and repairs on the METROLINK
Rail system. This is a 420 mile mainline railroad operating under
the following traffic conditions:
-
METROLINK -
206 passenger trains/day
-
Amtrak - 82
passenger trains/day
-
Union
Pacific/Southern Pacific - 58 freight trains/day
-
Burlington
Northern Santa Fe - 26 freight trains/day
This program
includes furnishing materials, complete installation, testing, and
commissioning of all rail signal and communications system upgrades
throughout various segments of the line. Additionally, it includes
providing "round-the-clock" signal maintenance that includes data
radio, microwave repeaters, fibre optic carrier transmission,
two-way radio, telephone, and various Public Address systems.
Burlington Northern
Santa Fe Railroad - Stampede Pass C&S Rehabilitation
MECRail recently completed a 150 mile signal system upgrade for
BNSF on their Stampede Pass route through the Cascade mountains in
Washington state. The project included the installation of 42 grade
crossings, 12 interlockings with switch heaters, 3 slide fences, and
6 hot box/dragging equipment detectors. All work was completed
under traffic conditions; was fast-tracked and completed in a record
6 months - on schedule and under budget. The particular nature of
this project required critical and detailed scheduling and
coordination with the railroad, suppliers, and other contractors
involved in bridge & structure construction, track rehabilitation,
and pedestrian and street traffic movements. MECRail was a
subcontractor on this project working through Harmon Industries.
CSX Transportation
Company - Indiana C&S Capacity Improvement Rehabilitation
MECRail currently provides installation supervision, inspection,
testing, and cut-over management for this 270 mile "double-tracking"
upgrade between Greenwich, Ohio and Chicago, Illinois.
Responsibilities include establishment of monthly, weekly, and daily
work plans and direction and supervision of CSXT and subcontractor
installation work crews ranging in size from 130 to 150 people.
MECRail is a subcontractor on this project working through Harmon
Industries.
Amtrak - North End
Electrification Project
This project has been particularly challenging because of
traffic frequency and scope requirements. It sets forth various
rules for use of/and access to the rail line and the maintenance of
uninterrupted passenger service during the construction period. The
route is divided into 28 blocks which are defined between
interlockings on the tracks and vary in length from less than one
(1) mile to more than eighteen (18) miles. Blocks are provided at
random times for construction activities while the railroad
"single-tracks" around construction crews. Each phase of
construction requires labor distribution, material fabrication and
layout, installation, cleanup, punch-listing, and testing. With
limited access, staging, and on-rail occupancy, the scheduling and
coordination of these linear operations must be done daily.
Installation of the electrification hardware is depended on the
linear progression made by the preceding foundation installation
operation during joint block occupancy. Pole and wiring crews must
work closely with foundation installation crews to ensure safety,
maximum work windows, limited interference and optimum efficiency
during all first pass activities. To accomplish this, all design
issues, conflicts, fabrication and delivery issues, surveys,
environmental provisions, installation activities, quality control
and assurance procedures, cleanup, and testing have all required
precision project management and implementation. MEC is a prime
contractor on this project working directly for the owner in a 50/50
joint venture.
The
above examples are representative of heavy-haul rail experience.
Additional experience has been acquired through transit & commuter
rail projects that have been completed by Mass. Electric
Construction Company (MEC) since the late 1950's and have totaled
in excess of US$1 billion. Currently, MEC is the largest installer
of transit and passenger rail based signal-communications and
traction power systems in the U.S. The company has worked on all
major transit properties and has acquired significant knowledge of
all major signal & communications equipment and technologies. |